MTI Access Project - Weekly Status w/e 28 November 08

Open PDF
Creating agency: GCHQ Government Communications Headquarters (UK)
Document date: 2008-11-28
Pages: 1
Genre: wiki
Banner:
Classification: TOP SECRET STRAP 1 COMINT
Dissemination: -

The document details the MTI Access Project’s status in November 2008, including a significant payment to GERONTIC, updates on organizational changes, and discussions about future access opportunities and cost reductions. This aligns with broader revelations about GERONTIC’s role in supporting GCHQ's surveillance operations, facilitating access to telecom infrastructure and shaping surveillance strategies.

Long Description:
This is a UK TOP SECRET STRAP1 COMINT GCHQ GCWiki page — a weekly status update for the MTI Access Project, week ending 28 November 2008, covering one named access programme and a Joint Management Board meeting with GERONTIC. VISAGE — tasking and requisition had been completed and a significant payment made to GERONTIC on 27 November, described as representing a significant chunk of project funding. This confirms the commercial nature of the arrangement — GCHQ was paying GERONTIC directly for access infrastructure rather than covertly intercepting traffic. The Joint Management Board meeting on 26 November between GCHQ and GERONTIC covered four items, all flagged as ECI-protected with a named contact for further details. GERONTIC provided an update on their new organisational structure — relevant to GCHQ's ongoing relationship management. BULLROARER node balancing was identified as a key work priority — BULLROARER appears to be a component of the access or switching infrastructure requiring load balancing across nodes. GERONTIC provided an update on future access and shaping opportunities — confirming that the commercial partner was proactively identifying new collection opportunities for GCHQ rather than simply fulfilling existing requirements. A new cost model for bandwidth delivery was reviewed, with initial indications suggesting it would reduce current rental costs by approximately 20% if applied immediately. The document reinforces the picture from other GCHQ access programme documents of GERONTIC as an active commercial partner with its own Joint Management Board structure, providing organisational updates, identifying new opportunities and negotiating cost models — a level of institutional integration well beyond passive compliance with legal orders.
Programs:
VISAGE, GERONTIC, BULLROARER

People mentioned:
-

Countries:
-

Tags:
GERONTIC JMB, GCWiki, MTI, Vodafone

Identifier:
28_November_08_redacted

PDF SHA-256:
11737148b9934eb213d1c6d25a63640ab9b62ffa7a2ce1969a7eb0cc57e3ed84

TOP SECRET STRAP1 COMINT
The maximum classification allowed on GCWiki is TOP SECRET STRAP1 COMINT. Click to report inappropriate
content.
For GCWiki help contact: [REDACTED] Support page

MTI Access Project - Weekly Status w/e 28 November 08

From GCWiki
Jump to: navigation, search

[edit] VISAGE

  • Tasking and Requisition completed.
  • Payment made to GERONTIC on Thursday 27th (equals a significant chunck of project funding).

[edit] Project

  • GERONTIC JMB (Wednesday 26th) - highlights include (Details ECI - please speak to [REDACTED] if you'd like more info):
    • Update from GERONTIC on their new organisational structure.
    • Prioritisation of key work (such as BULLROARER Node balancing).
    • Update from GERONTIC on future access and shaping opportunities.
    • Review of new cost model for bandwidth delivery (initial indications are that if this were to be applied now, it would reduce the current rental costs by approx 20%).
  • Project Risk & Issue review held.