MTI Access Project - Weekly Status w/e 27 June 08

Open PDF
Creating agency: GCHQ Government Communications Headquarters (UK)
Document date: 2008-06-27
Pages: 1
Genre: wiki
Banner:
Classification: TOP SECRET STRAP 1 COMINT
Dissemination: -

The document outlines the MTI Access Project’s progress, including the deployment of access equipment, risk reviews with GERONTIC, and internal testing of surveillance capabilities like DRUDGE and remote switching. This reflects broader revelations about how companies like Cable & Wireless (now Vodafone) facilitated GCHQ’s mass surveillance, including covert access to telecom networks like FLAG through systems like GERONTIC.

Long Description:
This is a UK TOP SECRET STRAP1 COMINT GCHQ GCWiki page — a weekly status update for the MTI Access Project, week ending 27 June 2008. The document covers three named access programmes, all involving GERONTIC — identified from other published Snowden documents as the codename for Vodafone Cable (formerly Cable and Wireless), one of GCHQ's primary commercial fibre access partners. GRASP — deployment of access equipment was scheduled for end of August in line with commercial timescales. A risk review was planned with GERONTIC to work through new deployment risks the company had identified. Egress funding was identified as a candidate for programme contingency budget, suggesting cost pressures on the egress infrastructure needed to carry collected data from the access point to GCHQ processing. DRUDGE — GERONTIC had been given circuits of interest for internal testing of the DRUDGE enabling capability. If testing was successful this would enable feasibility testing using a target system — suggesting DRUDGE was a new or developing access capability being trialled against live GERONTIC infrastructure before operational deployment. FAINT — a Work Package Agreement was being revised to include a GERONTIC remote switching proposal, suggesting a change to how traffic would be switched or selected at the access point. No further switches had been deployed that week, with all remaining switches planned for deployment before end of August. The document is notable for confirming that GERONTIC was actively involved in the technical planning and risk review of GCHQ access equipment deployment — consistent with the characterisation in other Snowden documents of GERONTIC as a willing commercial partner with dedicated Sensitive Relationship Teams supporting GCHQ access operations rather than a passive target of covert interception.
Programs:
GRASP, GERONTIC, DRUDGE, FAINT

People mentioned:
-

Countries:
-

Tags:
GCWiki, MTI, Vodafone

Identifier:
27_June_08_redacted

PDF SHA-256:
3880801903586439c24d5c1130295e53149a9a818c00c87eacba4f459c4b2d3d

TOP SECRET STRAP1 COMINT
The maximum classification allowed on GCWiki is TOP SECRET STRAP1 COMINT. Click to report inappropriate
content.
For GCWiki help contact: [REDACTED] Support page

MTI Access Project - Weekly Status w/e 27 June 08

From GCWiki
Jump to: navigation, search

[edit] GRASP

  • Deployment of access equipment scheduled for end August in line with commercial timescales.
  • Risk review on Monday with GERONTIC to review and work through potential new deployment risks identified
    by GERONTIC.
  • Egress funding identified as a possible candidate for funding under released Programme contingency budget.

[edit] DRUDGE

  • GERONTIC have been given ccts of interest for GERONTIC internal testing of the DRUDGE enabling
    capability.
  • If testing successful, this will enable feasibility testing using target system.

[edit] FAINT

  • WPA being revised to include the GERONTIC remote switching proposal.
  • No further switches have been deployed this week. All remaining switches planned for deployment before the
    end of August.