Mission Assurance Facility Phase 2 Completed

Open PDF
Creating agency: NSA National Security Agency (US)
Document date: 2004-07-29
Type: SIDtoday
Pages: 1
Genre: newsletter
Banner:
Classification: TOP SECRET
Dissemination: REL

A progress report on the construction of the Interim Mission Assurance Facility reveals that the second of four phases is complete. The site will protect SID's assets against catastrophic destruction.

Long Description:
This SIDtoday article reports the completion of Phase 2 of the Interim Mission Assurance Facility, an off-Fort Meade site intended to protect SID's processing and analysis assets against catastrophic destruction. Phase 1 had established the strategy, site, security, IT infrastructure, and replicated CES mission processing capability for the first time off the Fort Meade campus. Phase 2 added Analysis & Production, Customer Relationships, Finance, Business, HR, and Security systems, with the facility certified as a SCIF on July 23, 2004 and the first classified S2 system (mini-PINWALE) already arriving. The effort, conducted in four phases, remains on schedule and within budget.
Programs:
PINWALE, ITIS

People mentioned:
-

Countries:
-

Tags:
mission assurance, continuity, facility construction, SCIF, data processing, disaster recovery

Identifier:
2004-07-29_SIDToday_-_Mission_Assurance_Facility_Phase_2_Completed

PDF SHA-256:
fe8e08e4741a615a141a3ab874ee973c3da26fefcddbc6198414d84f8e37c5f4

DYNAMIC PAGE -- HIGHEST POSSIBLE CLASSIFICATION IS
TOP SECRET // SI / TK // REL TO USA AUS CAN GBR NZL

SIDtoday

(S//REL) Mission Assurance Facility Phase 2 Completed

FROM: [REDACTED] CES Systems Engineering Office (S3106)
Unknown
Run Date: 07/29/2004

(TS//REL) Another important milestone has been reached in the effort to protect SID's vital
processing and analysis assets against catastrophic destruction. Phase 2 of the Interim Mission
Assurance Facility, known as [REDACTED] has been completed on schedule.

(TS/REL) You may recall that [REDACTED] is to be accomplished in 4 phases. The focus of Phase 1 was
on developing the strategy, finding a Mission Assurance (MA) site, installing basic facilities,
security, and IT infrastructure, initiating our Intellectual Capital Recovery and replicating CES
(S31) mission processing capability off of the Fort Meade campus for the first time in NSA's 50
year history.

(TS//REL) Phase 2 has been the completion of some end-to-end threads by adding:

  • Analysis & Production (S2),
  • Customer Relationships (S1),
  • Finance,
  • Business,
  • HR, and
  • Security systems

(TS//REL) As projected, the facilities are ready to accept these systems. LF and the Army Corps
of Engineers (ACoE)has completed the construction of the facility. Q14 and Q15 (physical and
technical security) have certified Phase 2 as a SCIF as of July 23, 2004. Boxes and parts for the
first classified S2 system (mini-PINWALE) have already arrived at [REDACTED] Full mission population
will take many more months.

(TS//REL) We still have a long way to go. However, we remain on schedule,and within budget.
This would not have been possible without the excellent support from LF and the ACoE, ITIS,
Eagle Alliance, Security, and those in S1 and S2 who architected the systems.

(TS//REL) Although many challenges remain, due to the talent and dedication of countless
individuals throughout SID and our partner organizations each day brings SID closer and closer
to greater protection of our assets.

(U) See more on the reasons and phases for [REDACTED]

"(U//FOUO) SIDtoday articles may not be republished or reposted outside NSANet
without the consent of S0121 (DL sid comms)."

DYNAMIC PAGE -- HIGHEST POSSIBLE CLASSIFICATION IS
TOP SECRET // SI / TK // REL TO USA AUS CAN GBR NZL
DERIVED FROM: NSA/CSSM 1-52, DATED 08 JAN 2007 DECLASSIFY ON: 20320108